Project Update #2 - August 19, 2025

Est. 8/21/25 - Milling to begin on Lynnhaven from lift station to Freeport, Lorraine, Shalimar, Evaro, Seahorse and Brentlawn from Seahorse to Lorraine.

Est. start 8/22 thru 8/25/25: Pipe installation to begin at the lift station on Lynnhaven heading south, stopping at Freeport.

Est. start 8/25/25 (following the work above) pipe installation will start at the intersection of Lorraine and Lynnhaven, heading north on Lorraine.

Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.