Septic to Sewer

Share Septic to Sewer on Facebook Share Septic to Sewer on Twitter Share Septic to Sewer on Linkedin Email Septic to Sewer link

This page has been created to help Homeowners in the project area navigate through the construction process. Project updates will be posted below on a regular basis. All other project information can be found directly below or on the panel to the right.

Construction has begun!

Please subscribe to this page to get important notifications!


Project Background

As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).


Required Temporary Construction Easements (TCE)

Septic to Sewer FAQs


Understanding the Construction Process, i.e., How Will The Work Affect Me?


Each section of road worked on will consist of the following :

  1. Asphalt will be removed from the road, and driveway aprons will be trimmed at the right-of-way. Affected areas will be backfilled with lime rock or millings each day to maintain access to the residence.
  2. Pipes will be laid down the road starting where indicated on the project update map, working down to the section's end.
  3. Access to residences could be limited when work is being done in front of the property (cars will need to park away from the active construction area).
  4. Residents will be notified in advance of when work will affect access to their residence.
  5. Contractor will work with residents to provide ADA compliance when necessary.
  6. Roads will be repaved once the new sewer lines have been tested and approved for service.
  7. Any sprinkler systems damaged in the county right-of-way during the pipe installation portion of the project will be repaired during the road and right-of-way restoration process for your area.

Click below for Construction Notes for work to be done on your private property



NOTE re TRASH PICKUP

If you are experiencing interruptions of trash pickup in your area, please contact us so we can make arrangements for the cans to be moved to a nearby pickup area. The trash cans will be brought back to their original location at the end of the day by the contractor.



The New Sewer System in a Nutshell

During this project there are main 5 parts of the system being installed:

  • Service line – As part of this special project, service lines will be installed from your home to the cleanout which will be located at the right of way. The cleanout gives access if a need ever arises due to a stoppage or other reason.
  • Lateral – Lateral lines run from the cleanout to the main gravity main that runs under the road.
  • Gravity main – Gravity mains run under the road, they move sewage from the homes via gravity to a nearby lift stations.
  • Lift station – The lift station collects the sewage from the nearby gravity mains where it then gets sent to a wastewater treatment plant via pressurized force mains. There are 2 planned lift stations for this phase of the project.
  • Force main – Force mains run along the right-of-way, they are pressurized lines that move sewage from lift stations to the designated wastewater treatment plant.

Not all roads will have force mains installed; please view the map linked below to see which roads will have gravity mains, force mains or both running along them.

click to view larger



Project Updates Are Posted Below

Updated Project Schedule can be viewed under Project Documents for Reference

This page has been created to help Homeowners in the project area navigate through the construction process. Project updates will be posted below on a regular basis. All other project information can be found directly below or on the panel to the right.

Construction has begun!

Please subscribe to this page to get important notifications!


Project Background

As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).


Required Temporary Construction Easements (TCE)

Septic to Sewer FAQs


Understanding the Construction Process, i.e., How Will The Work Affect Me?


Each section of road worked on will consist of the following :

  1. Asphalt will be removed from the road, and driveway aprons will be trimmed at the right-of-way. Affected areas will be backfilled with lime rock or millings each day to maintain access to the residence.
  2. Pipes will be laid down the road starting where indicated on the project update map, working down to the section's end.
  3. Access to residences could be limited when work is being done in front of the property (cars will need to park away from the active construction area).
  4. Residents will be notified in advance of when work will affect access to their residence.
  5. Contractor will work with residents to provide ADA compliance when necessary.
  6. Roads will be repaved once the new sewer lines have been tested and approved for service.
  7. Any sprinkler systems damaged in the county right-of-way during the pipe installation portion of the project will be repaired during the road and right-of-way restoration process for your area.

Click below for Construction Notes for work to be done on your private property



NOTE re TRASH PICKUP

If you are experiencing interruptions of trash pickup in your area, please contact us so we can make arrangements for the cans to be moved to a nearby pickup area. The trash cans will be brought back to their original location at the end of the day by the contractor.



The New Sewer System in a Nutshell

During this project there are main 5 parts of the system being installed:

  • Service line – As part of this special project, service lines will be installed from your home to the cleanout which will be located at the right of way. The cleanout gives access if a need ever arises due to a stoppage or other reason.
  • Lateral – Lateral lines run from the cleanout to the main gravity main that runs under the road.
  • Gravity main – Gravity mains run under the road, they move sewage from the homes via gravity to a nearby lift stations.
  • Lift station – The lift station collects the sewage from the nearby gravity mains where it then gets sent to a wastewater treatment plant via pressurized force mains. There are 2 planned lift stations for this phase of the project.
  • Force main – Force mains run along the right-of-way, they are pressurized lines that move sewage from lift stations to the designated wastewater treatment plant.

Not all roads will have force mains installed; please view the map linked below to see which roads will have gravity mains, force mains or both running along them.

click to view larger



Project Updates Are Posted Below

Updated Project Schedule can be viewed under Project Documents for Reference

  • Project Update - October 10, 2025

    Share Project Update - October 10, 2025 on Facebook Share Project Update - October 10, 2025 on Twitter Share Project Update - October 10, 2025 on Linkedin Email Project Update - October 10, 2025 link

    Starting Monday, October 13th, road crews will be working on road base finishing along Shalimar, Brentlawn, Evaro, Lynnhaven to Lorraine, and Lorraine to Shalimar.

    Crews will begin gravity pipe installation along Lynnhaven mid-week; work will continue into the following week.

    Signs (shown below) will be posted in the front yards of properties the day before scheduled pipe installation will restrict driveway access for residents.


    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - October 3, 2025

    Share Project Update - October 3, 2025 on Facebook Share Project Update - October 3, 2025 on Twitter Share Project Update - October 3, 2025 on Linkedin Email Project Update - October 3, 2025 link

    Gravity main installation is complete along Shalimar Ave. and Evaro Ave.

    Road crews will be restoring road sub-bases along Shalimar Ave. and Evaro Ave. the week of October 6th.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - September 23, 2025

    Share Project Update - September 23, 2025 on Facebook Share Project Update - September 23, 2025 on Twitter Share Project Update - September 23, 2025 on Linkedin Email Project Update - September 23, 2025 link

    Milling and road prep for pipe installation on the following roads started 9/22. Crews are scheduled to work on the roads in the order shown as conditions/weather permits.

    • Lynnhaven Rd.
    • Lorraine Ln.
    • Shalimar Ave.
    • Evaro Ave.

    Signs (shown below) will be posted in the front yards of properties the day before scheduled pipe installation will restrict driveway access for residents.




    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage as far as possible beyond the barricades.


  • Project Update - September 11, 2025

    Share Project Update - September 11, 2025 on Facebook Share Project Update - September 11, 2025 on Twitter Share Project Update - September 11, 2025 on Linkedin Email Project Update - September 11, 2025 link

    Prep work and restoration of driveways along Freeport Dr. is scheduled for next week (weather dependent). Once driveways have been restored, sod restoration will begin.

    Crews will start pipe installation along the following roads on Monday, 9/15. Roads are scheduled to be worked on in the following order:

    • Lynnhaven Rd.
    • Lorraine Ln.
    • Shalimar Ave.
    • Evaro Ave.


    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - September 2, 2025

    Share Project Update - September 2, 2025 on Facebook Share Project Update - September 2, 2025 on Twitter Share Project Update - September 2, 2025 on Linkedin Email Project Update - September 2, 2025 link

    Paving of the following roads will begin on Thursday, September 4th. Work is estimated to last at least through next week (weather dependent).

    • Mountain Way Ave
    • Nantucket Lane
    • Montebello Lane
    • Northvale Street
    • Freeport Drive


    Barricades will be put up ahead of the work areas to prevent through traffic. Residents will be notified in advance when to expect their road to be paved. Residents should expect limited access to their residence based on active paving taking place on the road.



  • Project Update #2 - August 19, 2025

    Share Project Update #2 - August 19, 2025 on Facebook Share Project Update #2 - August 19, 2025 on Twitter Share Project Update #2 - August 19, 2025 on Linkedin Email Project Update #2 - August 19, 2025 link

    Est. 8/21/25 - Milling to begin on Lynnhaven from lift station to Freeport, Lorraine, Shalimar, Evaro, Seahorse and Brentlawn from Seahorse to Lorraine.

    Est. start 8/22 thru 8/25/25: Pipe installation to begin at the lift station on Lynnhaven heading south, stopping at Freeport.

    Est. start 8/25/25 (following the work above) pipe installation will start at the intersection of Lorraine and Lynnhaven, heading north on Lorraine.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

  • Project Update #1 - August 19, 2025

    Share Project Update #1 - August 19, 2025 on Facebook Share Project Update #1 - August 19, 2025 on Twitter Share Project Update #1 - August 19, 2025 on Linkedin Email Project Update #1 - August 19, 2025 link

    Est. 8/21/25 - Driveway restoration to begin on Nantucket, Montebello and Mountain Way.

    Est. 8/27/25 - Paving to begin on Nantucket, Montebello and Mountain Way.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - August 6, 2025

    Share Project Update - August 6, 2025 on Facebook Share Project Update - August 6, 2025 on Twitter Share Project Update - August 6, 2025 on Linkedin Email Project Update - August 6, 2025 link

    Road and pipe crews have begun work on Mountain Way Ave. starting at the north end (Freeport Dr.) working their way south, as well as the south end (Langan St.) working their way north.

    They are rebuilding the sub-base and adding limerock to stabilize the road. They will be rolling the road to compact it, there should be no vibration-type equipment being used.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

  • Project Update - July 29, 2025

    Share Project Update - July 29, 2025 on Facebook Share Project Update - July 29, 2025 on Twitter Share Project Update - July 29, 2025 on Linkedin Email Project Update - July 29, 2025 link

    Pipe crews are finishing up pipe work on Mountain Way south of Montebello.

    Road crews are working on getting Montebello back in shape.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - July 23, 2025

    Share Project Update - July 23, 2025 on Facebook Share Project Update - July 23, 2025 on Twitter Share Project Update - July 23, 2025 on Linkedin Email Project Update - July 23, 2025 link

    Crews will begin installing pipes and manholes along Northvale St. between Mountain Way Ave. and Sardinia Ave. The work is expected to continue for several days, weather dependent.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

Page last updated: 14 Oct 2025, 11:36 AM