Gravity Install, Gravity Services Install and Roadway Restoration will continue on Freeport and Lynnhaven.
Driveway Restoration - Lorraine, Lynnhaven and Sunday - 12/15 and 12/16
Paving/Sod Restoration is TENTATIVE for - Lorraine, Seahorse and Sunday - 12/15 till 12/19
Signs (shown below) will be posted in the front yards of properties the day before scheduled pipe installation will restrict driveway access for residents.

Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.