Project Update - January 16, 2026
Week of January 19 – January 23, 2026
Planned Work Activities:
Gravity Installation: Brentlawn St, Freeport Dr, Melshire Ave and Swan Ln
Roadway Restoration: Brentlawn St, Freeport Dr and Melshire Ave
Concrete Driveway Restoration: Brentlawn St and Freeport Dr
Fine Grading and Restoration will occur throughout the week as conditions allow.
Important Notice for Residents
Construction signs (shown below) will be placed in the front yards of affected properties one day prior to scheduled pipe installation.
During this time, driveway access will be temporarily restricted.