Project Update - January 23, 2026
Week of January 26 – January 30, 2026
Planned Work Activities:
Gravity Installation: Brentlawn St, Freeport Dr, Melshire Ave and Swan Ln
Roadway Restoration: Brentlawn St, Freeport Dr and Melshire Ave
Concrete Driveway Restoration: Brentlawn St, Freeport Dr, Melshire Ave and Swan Ln
Miscellaneous Restoration / Irrigations Repairs: will occur in the Sewer Shed 2 area
Important Notice for Residents
Construction signs (shown below) will be placed in the front yards of affected properties one day prior to scheduled pipe installation.
During this time, driveway access will be temporarily restricted.

Share Project Update - January 23, 2026 on Facebook
Share Project Update - January 23, 2026 on Twitter
Share Project Update - January 23, 2026 on Linkedin
Email Project Update - January 23, 2026 link