Week of January 26 – January 30, 2026

Planned Work Activities:

  • Gravity Installation: Brentlawn St, Freeport Dr, Melshire Ave and Swan Ln

  • Roadway Restoration: Brentlawn St, Freeport Dr and Melshire Ave

  • Concrete Driveway Restoration: Brentlawn St, Freeport Dr, Melshire Ave and Swan Ln

  • Miscellaneous Restoration / Irrigations Repairs: will occur in the Sewer Shed 2 area


Important Notice for Residents
Construction signs (shown below) will be placed in the front yards of affected properties one day prior to scheduled pipe installation.