Project Update - October 27, 2025

Crews are continuing to work on finishing road base along Shalimar, Brentlawn, Evaro, Lynnhaven to Lorraine and Lorraine to Shalimar.

Crews have been delayed prepping for pipe installation, but they hope to begin laying gravity pipe along Lynnhaven this week, to continue into the following week.

Signs (shown below) will be posted in the front yards of properties the day before scheduled pipe installation will restrict driveway access for residents.


Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


Share Project Update - October 27, 2025 on Facebook Share Project Update - October 27, 2025 on Twitter Share Project Update - October 27, 2025 on Linkedin Email Project Update - October 27, 2025 link
#<Object:0x0000000031de6008>