Prep work and restoration of driveways along Freeport Dr. is scheduled for next week (weather dependent). Once driveways have been restored, sod restoration will begin.

Crews will start pipe installation along the following roads on Monday, 9/15. Roads are scheduled to be worked on in the following order:

  • Lynnhaven Rd.
  • Lorraine Ln.
  • Shalimar Ave.
  • Evaro Ave.


Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.