Share Project Update - October 9, 2026 on Facebook
Share Project Update - October 9, 2026 on X (formerly Twitter)
Share Project Update - October 9, 2026 on Linkedin
Email Project Update - October 9, 2026 link
Week of October 9, 2026 – October 16, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Week of October 9, 2026 – October 16, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Share Project Update - October 2, 2026 on Facebook
Share Project Update - October 2, 2026 on X (formerly Twitter)
Share Project Update - October 2, 2026 on Linkedin
Email Project Update - October 2, 2026 link
Week of October 2, 2026 – October 9, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Week of October 2, 2026 – October 9, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Share Project Update - September 25, 2026 on Facebook
Share Project Update - September 25, 2026 on X (formerly Twitter)
Share Project Update - September 25, 2026 on Linkedin
Email Project Update - September 25, 2026 link
Week of September 25, 2026 – October 2, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Week of September 25, 2026 – October 2, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Share Project Update - September 18, 2026 on Facebook
Share Project Update - September 18, 2026 on X (formerly Twitter)
Share Project Update - September 18, 2026 on Linkedin
Email Project Update - September 18, 2026 link
Week of September 18, 2026 – September 25, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Week of September 18, 2026 – September 25, 2026
Important Project Information:
- Work will continue on Lift Station 6.
Share Project Update - September 11, 2026 on Facebook
Share Project Update - September 11, 2026 on X (formerly Twitter)
Share Project Update - September 11, 2026 on Linkedin
Email Project Update - September 11, 2026 link
Week of September, 11 2026 – September 18, 2026
Important Project Information:
- At this time, we anticipate the centralized sewer system for Sewer Shed 2 will be placed into service within the next six weeks. Residential sewer connections will begin shortly after. Please see additional information below regarding Temporary Constructions Easements and deadlines.
- If a TCE for the property has been signed:
The contractor’s construction schedule will determine when each property is connected to the new sewer system. The contractor will coordinate the work with the homeowner and ensure that all required project deadlines are met. At this time, we anticipate completion of all sewer connections within Sewer Shed 2 will take approximately four months. Sewer Shed 6 may take additional time to complete while the contractor completes Shed 2.
- If a TCE for the property has not been signed:
Pursuant to Hernando County Ordinance Sec. 28-238 and Florida Statute 381.00655, once the centralized sewer system is in place and in service, properties within the new sewer service area are required to connect. Property owners will have one year from the availability of sewer service to complete the connection. Property owners who have not signed the TCE will be notified via mail when sewer service is available.
Week of September, 11 2026 – September 18, 2026
Important Project Information:
- At this time, we anticipate the centralized sewer system for Sewer Shed 2 will be placed into service within the next six weeks. Residential sewer connections will begin shortly after. Please see additional information below regarding Temporary Constructions Easements and deadlines.
- If a TCE for the property has been signed:
The contractor’s construction schedule will determine when each property is connected to the new sewer system. The contractor will coordinate the work with the homeowner and ensure that all required project deadlines are met. At this time, we anticipate completion of all sewer connections within Sewer Shed 2 will take approximately four months. Sewer Shed 6 may take additional time to complete while the contractor completes Shed 2.
- If a TCE for the property has not been signed:
Pursuant to Hernando County Ordinance Sec. 28-238 and Florida Statute 381.00655, once the centralized sewer system is in place and in service, properties within the new sewer service area are required to connect. Property owners will have one year from the availability of sewer service to complete the connection. Property owners who have not signed the TCE will be notified via mail when sewer service is available.
Share Project Update - September 4, 2026 on Facebook
Share Project Update - September 4, 2026 on X (formerly Twitter)
Share Project Update - September 4, 2026 on Linkedin
Email Project Update - September 4, 2026 link
Week of September, 4 2026 – September 11, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Week of September, 4 2026 – September 11, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Share Project Update - August 28, 2026 on Facebook
Share Project Update - August 28, 2026 on X (formerly Twitter)
Share Project Update - August 28, 2026 on Linkedin
Email Project Update - August 28, 2026 link
Week of August 28, 2026 – September 4, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Week of August 28, 2026 – September 4, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Share Project Update - August 21, 2026 on Facebook
Share Project Update - August 21, 2026 on X (formerly Twitter)
Share Project Update - August 21, 2026 on Linkedin
Email Project Update - August 21, 2026 link
Week of August 21, 2026 – August 28, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Week of August 21, 2026 – August 28, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Share Project Update - August 14, 2026 on Facebook
Share Project Update - August 14, 2026 on X (formerly Twitter)
Share Project Update - August 14, 2026 on Linkedin
Email Project Update - August 14, 2026 link
Week of August 14, 2026 – August 21, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Week of August 14, 2026 – August 21, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Share Project Update - August 7, 2026 on Facebook
Share Project Update - August 7, 2026 on X (formerly Twitter)
Share Project Update - August 7, 2026 on Linkedin
Email Project Update - August 7, 2026 link
Week of August 7, 2026 – August 14, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.
Week of August 7, 2026 – August 14, 2026
Important Project Information:
- Work will continue on Lift Station 2 and Lift Station 6.