Septic to Sewer

Share Septic to Sewer on Facebook Share Septic to Sewer on Twitter Share Septic to Sewer on Linkedin Email Septic to Sewer link

This page has been created to help Homeowners in the project area navigate through the construction process. Project updates will be posted below on a regular basis. All other project information can be found directly below or on the panel to the right.

Construction has begun!

Please subscribe to this page to get important notifications!


Project Background

As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).


Required Temporary Construction Easements (TCE)

Septic to Sewer FAQs

Understanding the Construction Process, i.e., How Will The Work Affect Me?

Each section of road worked on will consist of the following :

  1. Asphalt will be removed from the road, and driveway aprons will be trimmed at the right-of-way. Affected areas will be backfilled with limerock or millings each day to maintain access to the residence.
  2. Pipes will be laid down the road starting where indicated on the project update map, working down to the section's end.
  3. Access to residences could be limited when work is being done in front of the property (cars will need to park away from the active construction area).
  4. Residents will be notified in advance of when work will affect access to their residence.
  5. Contractor will work with residents to provide ADA compliance when necessary.
  6. Project roads will be repaved toward the end of the project when all new sewer lines have been tested and released into service.

The New Sewer System in a Nutshell

During this project there are main 5 parts of the system being installed:

  • Service line – As part of this special project, service lines will be installed from your home to the cleanout which will be located at the right of way. The cleanout gives access if a need ever arises due to a stoppage or other reason.
  • Lateral – Lateral lines run from the cleanout to the main gravity main that runs under the road.
  • Gravity main – Gravity mains run under the road, they move sewage from the homes via gravity to a nearby lift stations.
  • Lift station – The lift station collects the sewage from the nearby gravity mains where it then gets sent to a wastewater treatment plant via pressurized force mains. There are 2 planned lift stations for this phase of the project.
  • Force main – Force mains run along the right-of-way, they are pressurized lines that move sewage from lift stations to the designated wastewater treatment plant.

Not all roads will have force mains installed; please view the map linked below to see which roads will have force mains running along them.

click to view larger



Project Updates Are Posted Below

Updated Project Schedule can be viewed under Project Documents for Reference

This page has been created to help Homeowners in the project area navigate through the construction process. Project updates will be posted below on a regular basis. All other project information can be found directly below or on the panel to the right.

Construction has begun!

Please subscribe to this page to get important notifications!


Project Background

As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).


Required Temporary Construction Easements (TCE)

Septic to Sewer FAQs

Understanding the Construction Process, i.e., How Will The Work Affect Me?

Each section of road worked on will consist of the following :

  1. Asphalt will be removed from the road, and driveway aprons will be trimmed at the right-of-way. Affected areas will be backfilled with limerock or millings each day to maintain access to the residence.
  2. Pipes will be laid down the road starting where indicated on the project update map, working down to the section's end.
  3. Access to residences could be limited when work is being done in front of the property (cars will need to park away from the active construction area).
  4. Residents will be notified in advance of when work will affect access to their residence.
  5. Contractor will work with residents to provide ADA compliance when necessary.
  6. Project roads will be repaved toward the end of the project when all new sewer lines have been tested and released into service.

The New Sewer System in a Nutshell

During this project there are main 5 parts of the system being installed:

  • Service line – As part of this special project, service lines will be installed from your home to the cleanout which will be located at the right of way. The cleanout gives access if a need ever arises due to a stoppage or other reason.
  • Lateral – Lateral lines run from the cleanout to the main gravity main that runs under the road.
  • Gravity main – Gravity mains run under the road, they move sewage from the homes via gravity to a nearby lift stations.
  • Lift station – The lift station collects the sewage from the nearby gravity mains where it then gets sent to a wastewater treatment plant via pressurized force mains. There are 2 planned lift stations for this phase of the project.
  • Force main – Force mains run along the right-of-way, they are pressurized lines that move sewage from lift stations to the designated wastewater treatment plant.

Not all roads will have force mains installed; please view the map linked below to see which roads will have force mains running along them.

click to view larger



Project Updates Are Posted Below

Updated Project Schedule can be viewed under Project Documents for Reference

  • Project Update - June 26, 2025

    Share Project Update - June 26, 2025 on Facebook Share Project Update - June 26, 2025 on Twitter Share Project Update - June 26, 2025 on Linkedin Email Project Update - June 26, 2025 link

    Montebello Lane Closure

    The highlighted area on the map below will be closed for pipe and manhole installation during the day starting June 27th thru July 1st. The road will be put back to passable driving conditions at the end of each work day.

  • Project Update - June 23, 2025

    Share Project Update - June 23, 2025 on Facebook Share Project Update - June 23, 2025 on Twitter Share Project Update - June 23, 2025 on Linkedin Email Project Update - June 23, 2025 link

    On Monday and Tuesday, June 23rd and 24th, crews will start milling the roads listed below. Signage will be placed at intersections as a warning of the roadwork, however the roads will remain passable for local residents.

    • Nantucket Lane
    • Montebello Lane
    • Northvale Street
    • Sardinia Avenue
    • Freeport Drive
    • Mountain Way Avenue


  • Project Update - June 12, 2025

    Share Project Update - June 12, 2025 on Facebook Share Project Update - June 12, 2025 on Twitter Share Project Update - June 12, 2025 on Linkedin Email Project Update - June 12, 2025 link

    The intersection at Freeport Dr. and Sunday Rd. will be closed today, 6/12 until 3pm this afternoon.


  • Project Update - May 16, 2025

    Share Project Update - May 16, 2025 on Facebook Share Project Update - May 16, 2025 on Twitter Share Project Update - May 16, 2025 on Linkedin Email Project Update - May 16, 2025 link

    *EXPECT TRAFFIC DELAYS IN ACTIVE CONSTRUCTION AREAS WITH CREWS, VEHICLES AND EQUIPMENT*

    Please note, weather or other unexpected circumstances could affect schedule. Any major deviations will be posted.

    The following activities are due to begin by (dates are approximate):

    • 5/14 - Moving equipment and crew into the area.
    • 5/14 - Install erosion control (silt fencing) and MOT (traffic maintenance notifications), i.e. traffice signs.
    • 5/20 - Prep work to begin for construction of lift station shown on map.
      • The lift station portion of the project is expected to extend into the Spring of 2026.
    • 5/26 - Trapping & relocation of gopher tortoises from lift station construction site.
    • 5/27 - Lynnhaven Rd. (yellow section on map) will start to be prepped for installation of sewer lines.
      • Work will start at Lorraine Ln., ending at Freeport Dr.
      • Work on this section of road is expected to last through the end of June.

    You need to be signed in to add your comment.

  • Project Update - May 5, 2025

    Share Project Update - May 5, 2025 on Facebook Share Project Update - May 5, 2025 on Twitter Share Project Update - May 5, 2025 on Linkedin Email Project Update - May 5, 2025 link

    Construction is scheduled to start on May 14th. Some activities to expect are below, which should minimally affect surrounding residents:

    • Installing silt fencing
    • Transporting supplies

    Truck activity will be noticed in the project area as supplies are brought into the project area.


    You need to be signed in to add your comment.

  • Hernando County Receives $12,250,000 Grant for Septic To Sewer

    Share Hernando County Receives $12,250,000 Grant for Septic To Sewer on Facebook Share Hernando County Receives $12,250,000 Grant for Septic To Sewer on Twitter Share Hernando County Receives $12,250,000 Grant for Septic To Sewer on Linkedin Email Hernando County Receives $12,250,000 Grant for Septic To Sewer link

    MEDIA RELEASE
    January 3, 2023

    Hernando County Receives $12,250,000 Grant for Septic To Sewer

    (Brooksville, FL) – At the August 23, 2022, Hernando County Board of County Commissioners (BOCC) meeting, the BOCC approved a grant award for $12,250,000 from the Florida Department of Environmental Protection (FDEP). The grant funding will be used to convert nearly 400 homes in Spring Hill from septic to sewer. The conversion from septic to sewer will help to reduce the negative impacts of nitrogen pollution in the water.


    The high levels of nitrates impact the Weeki Wachee Springs. The excess levels of nitrates cause an imbalance which leads to a growth of algae in the water. As a result, this can negatively impact the environment and can cause concern for public health, create foul beaches, inhibit navigation through the water, and reduce the aesthetic value of the resources.

    In 2018, a development of the basin management action plan (BMAP) was created. The trajectory of the BMAP was formed to meet the new requirements of the Florida Springs and Aquifer Protection Act. With this grant award, the Hernando County Utilities Department can begin taking strides to help the impact of the water quality and help reduce nitrates in these
    ecosystems.

    ###

  • Open House for Septic to Sewer Conversion Project

    Share Open House for Septic to Sewer Conversion Project on Facebook Share Open House for Septic to Sewer Conversion Project on Twitter Share Open House for Septic to Sewer Conversion Project on Linkedin Email Open House for Septic to Sewer Conversion Project link

    PUBLIC NOTICE

    July 28, 2022

    Hernando County Utilities Department
    to Host Open House for Septic to Sewer Conversion Project

    (Brooksville, FL) – The Hernando County Utilities Department (HCUD) will host an Open House on Wednesday, August 10th from 2pm to 6:30pm regarding the upcoming Septic to Sewer Conversion Project. Hernando County staff will be available between these hours to provide additional information and answer questions. The Open House will be held on the first floor of the HCUD administration building, located at 15365 Cortez Blvd., Brooksville, Florida 34613.

    In order to comply with the state mandated Basin Management Action Plan for Weeki Wachee Springs, Hernando County has been working on converting existing septic systems to centralized sewer. Septic systems represent 30% of the total nitrogen loading to groundwater. The conversion of septic systems to sanitary sewer will help remove a portion of the nitrogen to the Weeki Wachee Springs.

    The County was notified that the project will receive state grant funding for a portion of District A (see map). Local government and state grant funds will be used to pay for approximately 90% of the project costs. It is estimated that the remaining 10% of the costs will come from property assessments which can be paid over a period of 10 years.

    The Hernando Board of County Commissioners will consider the state funding agreements and the creation of a Municipal Services Benefit Unit at the regular Board Meeting scheduled for Tuesday, August 23, 2022, beginning at 9:00am in the Commission Chambers, Room 160 (20 North Main Street, Brooksville, Florida 34601).

    In accordance with the Americans With Disabilities Act, persons with disabilities needing a special accommodation to participate in these proceedings should contact Colleen Conko, Hernando County Administration, 15470 Flight Path Drive, Brooksville, Florida 34604, (352)754-4002. If hearing impaired, please call 1-800-676-3777.


    ###

Page last updated: 26 Jun 2025, 03:23 PM