Septic to Sewer

Share Septic to Sewer on Facebook Share Septic to Sewer on Twitter Share Septic to Sewer on Linkedin Email Septic to Sewer link

This page has been created to help Homeowners in the project area navigate through the construction process. Project updates will be posted below on a regular basis. All other project information can be found directly below or on the panel to the right.

Construction has begun!

Please subscribe to this page to get important notifications!


Project Background

As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).


Required Temporary Construction Easements (TCE)

Septic to Sewer FAQs


Understanding the Construction Process, i.e., How Will The Work Affect Me?


Each section of road worked on will consist of the following :

  1. Asphalt will be removed from the road, and driveway aprons will be trimmed at the right-of-way. Affected areas will be backfilled with limerock or millings each day to maintain access to the residence.
  2. Pipes will be laid down the road starting where indicated on the project update map, working down to the section's end.
  3. Access to residences could be limited when work is being done in front of the property (cars will need to park away from the active construction area).
  4. Residents will be notified in advance of when work will affect access to their residence.
  5. Contractor will work with residents to provide ADA compliance when necessary.
  6. Project roads will be repaved toward the end of the project when all new sewer lines have been tested and released into service.

Click below for Construction Notes for work to be done on your property



NOTE re TRASH PICKUP

To ensure scheduled trash pickup in areas affected by construction, trash cans will be moved by the contractor to the nearest street intersection for pick up. The trash cans will be brought back to their original location at the end of the day by the contractor.



The New Sewer System in a Nutshell

During this project there are main 5 parts of the system being installed:

  • Service line – As part of this special project, service lines will be installed from your home to the cleanout which will be located at the right of way. The cleanout gives access if a need ever arises due to a stoppage or other reason.
  • Lateral – Lateral lines run from the cleanout to the main gravity main that runs under the road.
  • Gravity main – Gravity mains run under the road, they move sewage from the homes via gravity to a nearby lift stations.
  • Lift station – The lift station collects the sewage from the nearby gravity mains where it then gets sent to a wastewater treatment plant via pressurized force mains. There are 2 planned lift stations for this phase of the project.
  • Force main – Force mains run along the right-of-way, they are pressurized lines that move sewage from lift stations to the designated wastewater treatment plant.

Not all roads will have force mains installed; please view the map linked below to see which roads will have force mains running along them.

click to view larger



Project Updates Are Posted Below

Updated Project Schedule can be viewed under Project Documents for Reference

This page has been created to help Homeowners in the project area navigate through the construction process. Project updates will be posted below on a regular basis. All other project information can be found directly below or on the panel to the right.

Construction has begun!

Please subscribe to this page to get important notifications!


Project Background

As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).


Required Temporary Construction Easements (TCE)

Septic to Sewer FAQs


Understanding the Construction Process, i.e., How Will The Work Affect Me?


Each section of road worked on will consist of the following :

  1. Asphalt will be removed from the road, and driveway aprons will be trimmed at the right-of-way. Affected areas will be backfilled with limerock or millings each day to maintain access to the residence.
  2. Pipes will be laid down the road starting where indicated on the project update map, working down to the section's end.
  3. Access to residences could be limited when work is being done in front of the property (cars will need to park away from the active construction area).
  4. Residents will be notified in advance of when work will affect access to their residence.
  5. Contractor will work with residents to provide ADA compliance when necessary.
  6. Project roads will be repaved toward the end of the project when all new sewer lines have been tested and released into service.

Click below for Construction Notes for work to be done on your property



NOTE re TRASH PICKUP

To ensure scheduled trash pickup in areas affected by construction, trash cans will be moved by the contractor to the nearest street intersection for pick up. The trash cans will be brought back to their original location at the end of the day by the contractor.



The New Sewer System in a Nutshell

During this project there are main 5 parts of the system being installed:

  • Service line – As part of this special project, service lines will be installed from your home to the cleanout which will be located at the right of way. The cleanout gives access if a need ever arises due to a stoppage or other reason.
  • Lateral – Lateral lines run from the cleanout to the main gravity main that runs under the road.
  • Gravity main – Gravity mains run under the road, they move sewage from the homes via gravity to a nearby lift stations.
  • Lift station – The lift station collects the sewage from the nearby gravity mains where it then gets sent to a wastewater treatment plant via pressurized force mains. There are 2 planned lift stations for this phase of the project.
  • Force main – Force mains run along the right-of-way, they are pressurized lines that move sewage from lift stations to the designated wastewater treatment plant.

Not all roads will have force mains installed; please view the map linked below to see which roads will have force mains running along them.

click to view larger



Project Updates Are Posted Below

Updated Project Schedule can be viewed under Project Documents for Reference

  • Project Update - July 29, 2025

    Share Project Update - July 29, 2025 on Facebook Share Project Update - July 29, 2025 on Twitter Share Project Update - July 29, 2025 on Linkedin Email Project Update - July 29, 2025 link

    Pipe crews are finishing up pipe work on Mountain Way south of Montebello.

    Road crews are working on getting Montebello back in shape.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - July 23, 2025

    Share Project Update - July 23, 2025 on Facebook Share Project Update - July 23, 2025 on Twitter Share Project Update - July 23, 2025 on Linkedin Email Project Update - July 23, 2025 link

    Crews will begin installing pipes and manholes along Northvale St. between Mountain Way Ave. and Sardinia Ave. The work is expected to continue for several days, weather dependent.

    Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

  • Project Update - July 22, 2025

    Share Project Update - July 22, 2025 on Facebook Share Project Update - July 22, 2025 on Twitter Share Project Update - July 22, 2025 on Linkedin Email Project Update - July 22, 2025 link

    Crews have been installing pipes and manholes along Mountain Way Ave. between Northvale St. and Freeport Dr. The work is expected to be done shortly depending on the weather.

    To discourage through traffic, barricades will be put up on Mountain Way at Freeport and Northvale. As always, local residents will be allowed passage beyond the barricades.


  • Project Update - July 17, 2025

    Share Project Update - July 17, 2025 on Facebook Share Project Update - July 17, 2025 on Twitter Share Project Update - July 17, 2025 on Linkedin Email Project Update - July 17, 2025 link

    Crews have begun installing pipes and manholes along Mountain Way Avenue, to continue through next week. They will start work at Montebello Lane, and head north to Northvale Street.

    To discourage through traffic, barricades will be put up on Mountain Way at Freeport Drive and Langan Street. As always, local residents will be allowed passage beyond the barricades.

  • Project Update - July 15, 2025

    Share Project Update - July 15, 2025 on Facebook Share Project Update - July 15, 2025 on Twitter Share Project Update - July 15, 2025 on Linkedin Email Project Update - July 15, 2025 link

    Crews will be moving onto Nantucket Lane tomorrow. Installation of pipes and manholes will continue until the entire section has been completed. Nantucket will be barricaded at Sardinia and Langan to discourage thru traffic; residents will be allowed to pass.

  • Project Update - July 7, 2025

    Share Project Update - July 7, 2025 on Facebook Share Project Update - July 7, 2025 on Twitter Share Project Update - July 7, 2025 on Linkedin Email Project Update - July 7, 2025 link

    The highlighted area on Montebello Lane will be closed for pipe and manhole installation starting July 7th. Work will start at the west end and continue east daily toward Nantucket until all manholes and piping are installed.

  • Project Update - July 1, 2025

    Share Project Update - July 1, 2025 on Facebook Share Project Update - July 1, 2025 on Twitter Share Project Update - July 1, 2025 on Linkedin Email Project Update - July 1, 2025 link

    Montebello Lane will be closed at Mountain Way Avenue on Wednesday, July 2nd. Crews will be finishing the deep pipe installation along Montebello up to the intersection.

  • Project Update - June 26, 2025

    Share Project Update - June 26, 2025 on Facebook Share Project Update - June 26, 2025 on Twitter Share Project Update - June 26, 2025 on Linkedin Email Project Update - June 26, 2025 link

    Montebello Lane Closure

    The highlighted area on the map below will be closed for pipe and manhole installation during the day starting June 27th thru July 1st. The road will be put back to passable driving conditions at the end of each work day.

  • Project Update - June 23, 2025

    Share Project Update - June 23, 2025 on Facebook Share Project Update - June 23, 2025 on Twitter Share Project Update - June 23, 2025 on Linkedin Email Project Update - June 23, 2025 link

    On Monday and Tuesday, June 23rd and 24th, crews will start milling the roads listed below. Signage will be placed at intersections as a warning of the roadwork, however the roads will remain passable for local residents.

    • Nantucket Lane
    • Montebello Lane
    • Northvale Street
    • Sardinia Avenue
    • Freeport Drive
    • Mountain Way Avenue


  • Project Update - June 12, 2025

    Share Project Update - June 12, 2025 on Facebook Share Project Update - June 12, 2025 on Twitter Share Project Update - June 12, 2025 on Linkedin Email Project Update - June 12, 2025 link

    The intersection at Freeport Dr. and Sunday Rd. will be closed today, 6/12 until 3pm this afternoon.


Page last updated: 30 Jul 2025, 10:11 AM