Project Background
As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).
Septic to Sewer FAQs![]() |
| ATTENTION |
|
Please subscribe to this page to get important notifications!
Project Background
As a result of the Florida Springs and Aquifer Protection Act signed into law by the Governor in July, 2016, Hernando County was tasked to find ways to comply with the requirements associated with the 2016 legislation and developed restoration plans (BMAPS). The Septic to Sewer Conversion Plan is Hernando County Utility Department's (HCUD) response to the state mandated Onsite Sewage Treatment and Disposal System Remediation Plan requirement for Weeki Wachee Springs (more detailed information can be found under Project Overview on side panel).
Septic to Sewer FAQs![]() |
| ATTENTION |
|
-
Project Update - October 3, 2025
Share Project Update - October 3, 2025 on Facebook Share Project Update - October 3, 2025 on X (formerly Twitter) Share Project Update - October 3, 2025 on Linkedin Email Project Update - October 3, 2025 linkGravity main installation is complete along Shalimar Ave. and Evaro Ave.
Road crews will be restoring road sub-bases along Shalimar Ave. and Evaro Ave. the week of October 6th.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
Gravity main installation is complete along Shalimar Ave. and Evaro Ave.
Road crews will be restoring road sub-bases along Shalimar Ave. and Evaro Ave. the week of October 6th.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
-
Project Update - September 23, 2025
Share Project Update - September 23, 2025 on Facebook Share Project Update - September 23, 2025 on X (formerly Twitter) Share Project Update - September 23, 2025 on Linkedin Email Project Update - September 23, 2025 linkMilling and road prep for pipe installation on the following roads started 9/22. Crews are scheduled to work on the roads in the order shown as conditions/weather permits.
- Lynnhaven Rd.
- Lorraine Ln.
- Shalimar Ave.
- Evaro Ave.
Signs (shown below) will be posted in the front yards of properties the day before scheduled pipe installation will restrict driveway access for residents.

Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage as far as possible beyond the barricades.
Milling and road prep for pipe installation on the following roads started 9/22. Crews are scheduled to work on the roads in the order shown as conditions/weather permits.
- Lynnhaven Rd.
- Lorraine Ln.
- Shalimar Ave.
- Evaro Ave.
Signs (shown below) will be posted in the front yards of properties the day before scheduled pipe installation will restrict driveway access for residents.

Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage as far as possible beyond the barricades.
-
Project Update - September 11, 2025
Share Project Update - September 11, 2025 on Facebook Share Project Update - September 11, 2025 on X (formerly Twitter) Share Project Update - September 11, 2025 on Linkedin Email Project Update - September 11, 2025 linkPrep work and restoration of driveways along Freeport Dr. is scheduled for next week (weather dependent). Once driveways have been restored, sod restoration will begin.
Crews will start pipe installation along the following roads on Monday, 9/15. Roads are scheduled to be worked on in the following order:
- Lynnhaven Rd.
- Lorraine Ln.
- Shalimar Ave.
- Evaro Ave.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
Prep work and restoration of driveways along Freeport Dr. is scheduled for next week (weather dependent). Once driveways have been restored, sod restoration will begin.
Crews will start pipe installation along the following roads on Monday, 9/15. Roads are scheduled to be worked on in the following order:
- Lynnhaven Rd.
- Lorraine Ln.
- Shalimar Ave.
- Evaro Ave.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
-
Project Update - September 2, 2025
Share Project Update - September 2, 2025 on Facebook Share Project Update - September 2, 2025 on X (formerly Twitter) Share Project Update - September 2, 2025 on Linkedin Email Project Update - September 2, 2025 linkPaving of the following roads will begin on Thursday, September 4th. Work is estimated to last at least through next week (weather dependent).
- Mountain Way Ave
- Nantucket Lane
- Montebello Lane
- Northvale Street
- Freeport Drive
Barricades will be put up ahead of the work areas to prevent through traffic. Residents will be notified in advance when to expect their road to be paved. Residents should expect limited access to their residence based on active paving taking place on the road.
Paving of the following roads will begin on Thursday, September 4th. Work is estimated to last at least through next week (weather dependent).
- Mountain Way Ave
- Nantucket Lane
- Montebello Lane
- Northvale Street
- Freeport Drive
Barricades will be put up ahead of the work areas to prevent through traffic. Residents will be notified in advance when to expect their road to be paved. Residents should expect limited access to their residence based on active paving taking place on the road.
-
Project Update #2 - August 19, 2025
Share Project Update #2 - August 19, 2025 on Facebook Share Project Update #2 - August 19, 2025 on X (formerly Twitter) Share Project Update #2 - August 19, 2025 on Linkedin Email Project Update #2 - August 19, 2025 linkEst. 8/21/25 - Milling to begin on Lynnhaven from lift station to Freeport, Lorraine, Shalimar, Evaro, Seahorse and Brentlawn from Seahorse to Lorraine.
Est. start 8/22 thru 8/25/25: Pipe installation to begin at the lift station on Lynnhaven heading south, stopping at Freeport.
Est. start 8/25/25 (following the work above) pipe installation will start at the intersection of Lorraine and Lynnhaven, heading north on Lorraine.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

Est. 8/21/25 - Milling to begin on Lynnhaven from lift station to Freeport, Lorraine, Shalimar, Evaro, Seahorse and Brentlawn from Seahorse to Lorraine.
Est. start 8/22 thru 8/25/25: Pipe installation to begin at the lift station on Lynnhaven heading south, stopping at Freeport.
Est. start 8/25/25 (following the work above) pipe installation will start at the intersection of Lorraine and Lynnhaven, heading north on Lorraine.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

-
Project Update #1 - August 19, 2025
Share Project Update #1 - August 19, 2025 on Facebook Share Project Update #1 - August 19, 2025 on X (formerly Twitter) Share Project Update #1 - August 19, 2025 on Linkedin Email Project Update #1 - August 19, 2025 linkEst. 8/21/25 - Driveway restoration to begin on Nantucket, Montebello and Mountain Way.
Est. 8/27/25 - Paving to begin on Nantucket, Montebello and Mountain Way.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
Est. 8/21/25 - Driveway restoration to begin on Nantucket, Montebello and Mountain Way.
Est. 8/27/25 - Paving to begin on Nantucket, Montebello and Mountain Way.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
-
Project Update - August 6, 2025
Share Project Update - August 6, 2025 on Facebook Share Project Update - August 6, 2025 on X (formerly Twitter) Share Project Update - August 6, 2025 on Linkedin Email Project Update - August 6, 2025 linkRoad and pipe crews have begun work on Mountain Way Ave. starting at the north end (Freeport Dr.) working their way south, as well as the south end (Langan St.) working their way north.
They are rebuilding the sub-base and adding limerock to stabilize the road. They will be rolling the road to compact it, there should be no vibration-type equipment being used.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

Road and pipe crews have begun work on Mountain Way Ave. starting at the north end (Freeport Dr.) working their way south, as well as the south end (Langan St.) working their way north.
They are rebuilding the sub-base and adding limerock to stabilize the road. They will be rolling the road to compact it, there should be no vibration-type equipment being used.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

-
Project Update - July 29, 2025
Share Project Update - July 29, 2025 on Facebook Share Project Update - July 29, 2025 on X (formerly Twitter) Share Project Update - July 29, 2025 on Linkedin Email Project Update - July 29, 2025 linkPipe crews are finishing up pipe work on Mountain Way south of Montebello.
Road crews are working on getting Montebello back in shape.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
Pipe crews are finishing up pipe work on Mountain Way south of Montebello.
Road crews are working on getting Montebello back in shape.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.
-
Project Update - July 23, 2025
Share Project Update - July 23, 2025 on Facebook Share Project Update - July 23, 2025 on X (formerly Twitter) Share Project Update - July 23, 2025 on Linkedin Email Project Update - July 23, 2025 linkCrews will begin installing pipes and manholes along Northvale St. between Mountain Way Ave. and Sardinia Ave. The work is expected to continue for several days, weather dependent.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

Crews will begin installing pipes and manholes along Northvale St. between Mountain Way Ave. and Sardinia Ave. The work is expected to continue for several days, weather dependent.
Barricades will be put up ahead of the work areas to discourage through traffic. As always, local residents will be allowed passage beyond the barricades.

-
Project Update - July 22, 2025
Share Project Update - July 22, 2025 on Facebook Share Project Update - July 22, 2025 on X (formerly Twitter) Share Project Update - July 22, 2025 on Linkedin Email Project Update - July 22, 2025 linkCrews have been installing pipes and manholes along Mountain Way Ave. between Northvale St. and Freeport Dr. The work is expected to be done shortly depending on the weather.
To discourage through traffic, barricades will be put up on Mountain Way at Freeport and Northvale. As always, local residents will be allowed passage beyond the barricades.

Crews have been installing pipes and manholes along Mountain Way Ave. between Northvale St. and Freeport Dr. The work is expected to be done shortly depending on the weather.
To discourage through traffic, barricades will be put up on Mountain Way at Freeport and Northvale. As always, local residents will be allowed passage beyond the barricades.

Follow Project
Frequently Asked Questions
Upcoming Events
Project Staff
-
CH
Phone 352-540-4368 ext 35130 Email chiggins@hernandocounty.us -
JB
Phone 352-540-4368 ext 35859 Email jbedingfield@co.hernando.fl.us
Project Documents for Reference
Videos
-
Click here to play video
How Septic Systems Impact Springs
Take 90 seconds to learn how septic systems can affect the springs.
-
Click here to play video
Florida's Aquifer Adventure
Video discusses Florida's aquifer and related topics
@13:50 How contaminants affect the springs & aquifer
@16:35 Springs Initiative